Create Your First Hello World Flow

For the complete documentation index, see llms.txt. For a full content snapshot, see llms-full.txt. Append .md to any kestra.io/docs/* URL for plain Markdown.

Start by building a simple Hello World flow.

Build your first Hello World Flow

Flows

Flows are defined in a declarative YAML syntax to keep the orchestration code portable and language-agnostic.

Each flow consists of three required components: id, namespace, and tasks.

  1. id is the unique identifier of the flow.
  2. namespace separates projects, teams, and environments.
  3. tasks is a list of tasks executed in order.

Here are those three components in a YAML file:

id: getting_started
namespace: company.team
tasks:
- id: hello_world
type: io.kestra.plugin.core.log.Log
message: Hello World!

The id of a flow must be unique within its namespace. For example:

  • ✅ You can have a flow named getting_started in company.team1 and another flow named getting_started in company.team2.
  • ❌ You cannot have two flows named getting_started in company.team at the same time.

The combination of id and namespace is the unique identifier for a flow.

Namespaces

Namespaces are used to group flows and provide structure. Keep in mind that a flow’s allocation to a namespace is immutable. Once a flow is created, you cannot change its namespace. If you need to change the namespace of a flow, create a new flow within the desired namespace and delete the old flow.

Labels

To add another layer of organization, use labels to group flows with key-value pairs. In short, labels are customizable tags to simplify monitoring and filtering of flows and executions. For example, taking the flow above, we can add a label with the key tag to define the flow as Getting Started:

id: getting_started
namespace: company.team
labels:
tag: Getting Started
tasks:
- id: hello_world
type: io.kestra.plugin.core.log.Log
message: Hello World!

Descriptions

You can optionally add a description property to document your flow’s purpose or other useful information. The description is a string that supports markdown syntax. This markdown description is rendered and displayed in the UI.

Here is the same flow as before, but with labels and descriptions:

id: getting_started
namespace: company.team
description: |
# Getting Started
Let's `write` some **markdown** - [first flow](https://t.ly/Vemr0) 🚀
labels:
tag: Getting Started
tasks:
- id: hello_world
type: io.kestra.plugin.core.log.Log
message: Hello World!
description: |
## About this task
This task prints "Hello World!" to the logs.

Learn more about flows in the Flows page.

Tasks

Now that you know how to document and organize your flows, it’s time to get to the core of orchestration: tasks.

Tasks are atomic actions in your flows. You can design your tasks to be small and granular, such as fetching data from a REST API or running a self-contained Python script. However, tasks can also represent large and complex processes, like triggering containerized processes or long-running batch jobs (e.g., using dbt, Spark, AWS Batch, Azure Batch, etc.) and waiting for their completion.

Task execution order

Tasks are defined as a list. By default, all tasks in the list will be executed sequentially — the second task will start as soon as the first one finishes successfully.

Kestra provides additional customization to run tasks in parallel, iterate (sequentially or in parallel) over a list of items, or allow specific tasks to fail without stopping the flow. These kinds of actions are called Flowable tasks because they define the flow logic. We’ll cover Flowable tasks in more detail later in the tutorial, but for now it is good to know they exist.

A task in Kestra must have an id and a type. This is similar to how a flow must have an id and a namespace. Other task properties depend on the task type. You can think of a task as a step in a flow that executes a specific action, such as running a Python or Node.js script in a Docker container or loading data from a database.

We’ve shown a Log task in some example flows before, and below is the same flow with an additional Python script task added. The Log task runs first and then the Python task (copy and run for yourself to see the results):

id: getting_started
namespace: company.team
description: |
# Getting Started
Let's `write` some **markdown** - [first flow](https://t.ly/Vemr0) 🚀
labels:
tag: Getting Started
tasks:
- id: hello_world
type: io.kestra.plugin.core.log.Log
message: Hello World!
description: |
## About this task
This task prints "Hello World!" to the logs.
- id: python
type: io.kestra.plugin.scripts.python.Script
containerImage: python:slim
script: |
print("Hello World!")

Iterate quickly with Playground

When you want to tweak a flow step by step without rerunning everything, use the Playground in the editor. It lets you play tasks one at a time, keep prior outputs, and iterate like a notebook. See the short guide in UI → Playground and try it with the getting_started example above before moving on.

Autocompletion

Kestra supports hundreds of tasks integrating with various external systems. It’s neither necessary nor possible to memorize all potential tasks or properties, maybe one day. Use the shortcut CTRL + SPACE on Windows/Linux or fn + control + SPACE on macOS to trigger autocompletion and list available tasks or properties for a given task. Kestra also has built-in documentation accessible through the UI for Flow, Task, and Trigger properties, so you don’t have to context switch between building a flow and learning the ins and outs of a component.

Create and run a flow

To this point, we have shown some flows to run and get familiar with. Now, let’s create a flow to use throughout the rest of the tutorial. Open the Flows view and click + Create:

Create flow

Paste the following code into the Flow editor:

id: getting_started
namespace: company.team
tasks:
- id: api
type: io.kestra.plugin.core.http.Request
uri: https://dummyjson.com/products

Then, hit the Save button, or you can also save as a draft in case you’d like to keep editing.

Create flow

This flow has a single task that fetches data from the dummyjson API via an HTTP Request task. Run it with the Execute button to see the output.

After execution, you’ll be directed to the Gantt view to see the stages of your flow’s progress. In this simple example, we see the API request successfully execute.

gantt view

Toggle over to the Execution Overview for a visualization of your flow tasks and explore the other post-execution tabs for even more detailed information about your run.

execution overview

While fetching data is a great first step, it is just that, a first step. In the next sections, you’ll explore the other critical components of Kestra flows: Inputs, Outputs, Triggers, and more.

Was this page helpful?